New BATE stadium 50% done (photo)
The construction will be finished in the second half of 2013.
The stands and columns have been installed recently. Now the builders are waiting for warmer weather to start active work.
The construction has been delayed a little. Deputy governor of Minsk Province Anatol Mirchuk arrived in Barysau to study the reasons for it, the First TV channel reports. Many problems were caused by "the parallel designing method" – the object had not received all the project documents so far.
The new stadium will be the 4th UEFA category. It will allow the highest level matches including semi-finals of the Champions League to be played in Barysau.